You can build a Gantt chart with calendar with the help of the Gantt chart type. |
You need to create a Gantt chart with calendar (to show working days by weeks at the bottom of the chart).
Your source tables look like the tables below. The first one can be manually created or come from Jira (you can use the Jira Issues macro, we mean).
Sprint | Key | Start | End | Completion Ratio |
---|---|---|---|---|
Sprint 1 | ECS-93 | 10 Mar 2025 | 13 Mar 2025 | 100% |
Sprint 1 | ECS-48 | 15 Mar 2025 | 22 Mar 2025 | 100% |
Sprint 1 | ECS-62 | 10 Mar 2025 | 29 Mar 2025 | 100% |
Sprint 2 | ECS-61 | 15 Mar 2025 | 22 Mar 2025 | 80% |
Sprint 2 | ECS-99 | 24 Mar 2025 | 29 Mar 2025 | 70% |
Sprint | Milestone | Date |
---|---|---|
Sprint 1 | RC-1 | 19 Mar 2025 |
Sprint 2 | RC-2 | 26 Mar 2025 |
Event | Date |
---|---|
Today | today |
AP-40 | 18 Mar 2025 |
EP-20 | 26 Mar 2025 |
Calendar | Weeks | C.start | C.end |
---|---|---|---|
Calendar | Week 1 | 10 Mar 2025 | 15 Mar 2025 |
Calendar | Week 2 | 17 Mar 2025 | 22 Mar 2025 |
Calendar | Week 3 | 24 Mar 2025 | 29 Mar 2025 |