This version of the app's documentation is outdated. Please find the information you're looking for here:
Visualizing of the Amount of Planned and Spent Time Within the Project
Visualizing of the Amount of Planned and Spent Time Within the Project
The Source Table:
The Result:
Macro combination:
Insert the
Jira Issues
macro.
Wrap the Jira Issues macro in the
Table Filter
macro.
Wrap the Table Filter macro in the
Pivot Table
macro.
Wrap the Pivot Table macro in the
Chart from Table
macro.
Macro configuration:
Table Filter:
Filter Column
Status
Filter Type
Dropdown
Filter Values
Done
Pivot Table:
Row Labels
T
Column Labels
-
Calculated Column
Original Estimate, Time Spent
Operation Type
Sum
Chart from Table:
Type
Bar
Labels Column
T
Values Column
Sum of Original Estimate, Sum of Time Spent