Use case
You have a table containing a period of time (start date and end date). You need to count the number of workdays during this time period.
More Advanced option:
You have an additional table with national holidays which you also shouldn't consider as workdays.
Solution
- Switch the page to the edit mode.
- Insert the Table Transformer macro and paste the table within the macro body.
- Select the macro and click Edit.
- Switch to the SQL query tab.
Enter the following SQL query:
SELECT *, 'Days' - 2 * (('Days' / 7)::integer) - CASE WHEN 'Days' % 7 = 0 THEN 0 WHEN 'Start date'::Date->getDay() = 0 THEN 1 WHEN 'Start date'::Date->getDay() + 'Days' % 7 = 7 THEN 1 WHEN 'Start date'::Date->getDay() + 'Days' % 7 > 7 THEN 2 ELSE 0 END AS 'Work days' FROM (SELECT *, ROUND((T1.'End date' - T1.'Start date') / "1d") + 1 AS 'Days' FROM T1)- Click Next.
- Set the worklog settings.
- Save the macro and the page.
You can use FORMATWIKI function for the purposes of cell formatting.
For the advanced use case option
Enter the following SQL query:
SELECT *,
'Days' - 2 * (('Days' / 7)::integer) -
CASE
WHEN 'Days' % 7 = 0 THEN 0
WHEN 'Start date'::Date->getDay() = 0 THEN 1
WHEN 'Start date'::Date->getDay() + 'Days' % 7 = 7 THEN 1
WHEN 'Start date'::Date->getDay() + 'Days' % 7 > 7 THEN 2
ELSE 0
END
-
(SELECT COUNT(*) FROM
(SELECT *,'Holiday'::Date->getDay() AS 'Day' FROM T2)
WHERE 'Holiday' >= TT.'Start date' AND 'Holiday' <= TT.'End date'
AND 'Day' > 0 AND 'Day' < 6)
AS 'Work days'
FROM
(SELECT *, ROUND(('End date' - 'Start date') / "1d") + 1 AS 'Days' FROM T1) AS TT